Performance measurement using overall equipment and resource effectiveness - A concrete block manufacturing case study

Authors

  • Huthaifa Alkhazraji University of Technology, Baghdad, Iraq
  • Sohaib Khlil Engineering Technical College - Baghdad, Middle Technical University, Baghdad, Iraq
  • Zina Alabacy University of Technology, Baghdad, Iraq

DOI:

https://doi.org/10.51173/jt.v1i1.85

Keywords:

Overall Equipment Effectiveness, Overall Resource Effectiveness, Concrete Block Manufacturing, Total Productive Maintenance

Abstract

Companies are required to integrate a set of critical dimensions in order to measure and evaluate their performance to compete in globally competitive markets. Overall Equipment Effectiveness (OEE) is a quantitative metric, in the context of the total productive maintenance (TPM), attempts to measure and improve the effectiveness of manufacturing operations in three dimensions namely: availability, performance rate and quality rate. This study applies OEE to evaluate and improve the performance of a concrete block manufacturing system at Dler Company in Iraq. The study was conducted in two years of operation during 2016 and 2017. Results from 2016 show that the level of effectiveness was lower than the world class. An improvement in the average value of the OEE for 2017 was recorded, where the OEE value is increased in 2017 to 75% in comparison with its value in 2016 at 67%. It was also found that the reasons for this improvement are due to the enhancement that are made in the availability and quality.

Downloads

Download data is not yet available.

Author Biographies

Huthaifa Alkhazraji, University of Technology, Baghdad, Iraq

Control and System Engineering Department

Sohaib Khlil, Engineering Technical College - Baghdad, Middle Technical University, Baghdad, Iraq

Department of Applied Mechanics

Zina Alabacy, University of Technology, Baghdad, Iraq

Control and System Engineering Department

References

R. M. Nachiappa and N. Anantharaman, “Evaluation of overall line effectiveness (OLE) in a continuous product line manufacturing system,” Journal of Manufacturing Technology Management, vol.17, no.7, pp. 987-1008, 2006

R. Wudhikarn, “Implementation of overall equipment effectiveness in wire mesh manufacturing,” In IEEE International Conference Industrial Engineering and Engineering Management (IEEM), 819-823, 2011

R. W. Schmenner and T. E. Vollmann, “Performance measures: gaps, false alarms, and the “usual suspects”,” International Journal of Operations & Production Management, vol.14, no.12, pp. 58-69, 1994

P. Jonsson and M. Lesshammar, “Evaluation and improvement of manufacturing performance measurement systems-the role of OEE,” International Journal of Operations & Production Management, vol.19, no.1,pp. 55-78, 1999

S. Nakajima, An Introduction to TPM, Productivity Press, Cambridge, MA, 1988.

A. Bangar, H. Sahu and J. Batham, “Improving overall equipment effectiveness by implementing total productive maintenance in auto industry,” International Journal of emerging technology and advanced engineering, vol.3, no.6, pp.590-594, 2013

S. D. Kalpande, “OEE an effective tool for TPM implementation-A case study,” Asset Management & Maintenance Journal, vol.27, no.5, pp. 46,2014

Z. H. Abdullah and L. M. Dawood, “Study Impact of Overall Equipment and Resource Effectiveness onto Cement Industry,” Journal of University of Babylon, vol.26, no.3,pp. 187-198,2018

P. Muchiri and L. Pintelon, “Performance measurement using overall equipment effectiveness (OEE): literature review and practical application discussion,” International journal of production research, vol.46, no.13, pp.3517-3535,2008

B. Dal, P. Tugwell and R. Greatbanks, “Overall equipment effectiveness as a measure of operational improvement–a practical analysis,” International Journal of Operations & Production Management, vol.20, no.12, pp.1488-1502, 2000

O. T. R. Almeanazel, “Total productive maintenance review and overall equipment effectiveness measurement,” JJMIE, vol.4, no.4, pp.517-522, 2010

I. H. Afefy, “Implementation of total productive maintenance and overall equipment effectiveness evaluation,” International Journal of Mechanical & Mechatronics Engineering, vol.13, no.1, pp. 69-75, 2013

S. R. Vijayakumar and S. Gajendran, “Improvement of overall equipment effectiveness (OEE) in injection moulding process industry,” IOSR J Mech Civil Eng, vol.2, no.10, pp. 47-60, 2014

P. H. Tsarouhas, “Evaluation of maintenance management through the overall equipment effectiveness of a yogurt production line in a medium-sized Italian company,” International Journal of Productivity and Quality Management, vol.16, no.3, pp.298-311, 2015

M. A. Sahib and L. M. Dawood, “Analysis of Production System Effectiveness Elements,” Engineering and Technology Journal, vol.36, no. 8 Part (A) Engineering, pp. 832-841, 2018

K.G. Eswaramurthi and P.V. Mohanram, “Improvement of manufacturing performance measurement system and evaluation of overall resource effectiveness,” American Journal of Applied Sciences, vol.10, no.2, pp.131-138, 2013

Downloads

Published

2019-12-31

How to Cite

Alkhazraji, H., Khlil, S., & Alabacy, Z. (2019). Performance measurement using overall equipment and resource effectiveness - A concrete block manufacturing case study. Journal of Techniques, 1(1), 6–17. https://doi.org/10.51173/jt.v1i1.85